Station 43 Update

Posted: 16-May-2018 Progress on the Station 43 construction progress is continuing according to schedule. Today marked a critical milestone as 36 reinforced concrete piers were drilled and poured. Each pier is 20’ deep and 2’ wide and, due to the soil composition, were drilled and immediately poured. This is a complex operation on any project and was made even more challenging by the small size of our job site and the number of people and vehicles required to carry it out.